A contractor in the UAE or Saudi Arabia runs every project on the same documents: the bill of quantities (BOQ) from the tender, the advance payment and its recovery, monthly interim payment certificates, variations, retention on both sides, subcontractor certificates and the cost of the site team. In many companies each of these lives in its own spreadsheet, and the project's real margin only shows up at the end.
We took one invented project through Odoo 20, from the tender to the second interim payment, to see how much of this standard Odoo handles and where it needs setup or added features.


Our test
We ran the test on an Odoo 20 Enterprise test database for a UAE company, so amounts are in AED with 5% VAT. The contractor, client, consultant, subcontractors, quantities and rates are invented, and the dates run from September to November 2026. The project is a G+4 residential building in Al Furjan, Dubai, tendered at AED 6.6 million before VAT. The rates, percentages and terms in this article are examples for the test. Your contracts set the real ones.
1. The tender and the BOQ
We followed the tender in CRM with a pipeline of its own: tender received, pricing, submitted and awarded. The consultant, the tender documents and the submission date sat on the opportunity, and its expected value updated itself from the quotation.
The BOQ became the quotation. We imported it from a spreadsheet with Odoo's standard import, sections and lines together: preliminaries, earthworks, concrete, masonry, MEP and finishes, with quantities in m³, m² or lump sum. Odoo showed a subtotal for each section, and because each BOQ item carries a cost, the quotation also showed the margin, 19.4% on this tender.

Two things to know. The import filled every column we gave it, so an empty description column left the lines without a description; put the item description in the file. And each BOQ item has one cost. A cost sheet that breaks an item into materials, labour, equipment and overheads, the way estimators price a tender, isn't part of standard Odoo.
2. The contract, the project and the programme
Confirming the quotation turned it into the contract and created the project, with one task for each BOQ item, linked to its contract line. We planned the tasks in the Gantt view with their dependencies, so moving the excavation moves everything that waits for it.

That covers a site programme. Contractors who plan in Primavera or Microsoft Project will want the two kept in step, and Odoo doesn't import their schedule files as standard.
We also gave the project a cost budget of AED 5.3 million. Odoo compares it with the actual costs as they come in: 12.9% used by the end of November. The budget is one amount for the project. A budget per BOQ item, or per cost type such as materials, labour and subcontracts, needs more setup or an addition.
3. The advance payment
The client paid a 10% advance, AED 660,390 before VAT, and Odoo invoiced it from the contract in two clicks.
One setting matters here. By default Odoo posted the advance to the sales account, so the project counted it as revenue in September before any work was done. Set a down payment account in the accounting settings, a liability for advances from customers, so advances stay off your revenue until the work is certified.
4. Subcontractor bids
We put the MEP package out to three subcontractors. Odoo 20 keeps the bids together as alternatives on one request for quotation, with the Purchase Alternative app, so you see all three side by side and the total of each.

We awarded the package to the lowest bidder and the other two were cancelled. Odoo compares bids on price, the expected date and the vendor's on-time delivery record. Scoring subcontractors on quality, safety or past performance, and a portal where they submit their bids, would have to be added.
5. The subcontractor's progress bill
At the end of November the MEP subcontractor certified 30% of the package. With the subcontract set to bill on received quantities, entering 0.30 as received produced a bill for AED 615,000. We added a line holding back 10% retention, AED 61,500, on a retentions payable account.

Our first attempt billed the whole package, because the subcontract was set to bill on ordered quantities. Check that setting on every subcontract. The retention line is typed by hand on each bill, and so is its release at the end.
6. Site labour
The site engineer, foreman, mason and steel fixer logged their hours against the BOQ tasks. With an hourly cost on each employee, the 1,344 hours went into the project's costs as AED 73,728.
Two things construction companies in the Gulf ask for aren't in standard Odoo: managing labour camps and accommodation, and spreading each worker's salary over the projects they worked on by days. Both are common additions.
7. Interim payments and a variation
For each interim payment, the quantity surveyor entered the measured quantity on each BOQ line of the contract, and Odoo invoiced what had been done since the last invoice. October's certificate came to AED 158,400 of work.
In November the consultant instructed a variation, a rooftop shade structure for AED 85,000. We added it to the signed contract as its own section, and Odoo created a task for it in the project. Forty per cent of it was done by the end of the month, so November's certificate carried AED 516,000 of work including AED 34,000 for the variation.

Each certificate recovered 10% of its value from the advance and held back 10% retention, and this is where Odoo needs help. Standard Odoo deducts the whole advance from the next invoice. We turned that off and added the recovery and the retention as lines on each invoice, with the recovery carrying VAT so the tax already charged on the advance isn't charged twice. Agree that treatment with your tax adviser.
The invoice also shows only this period. A payment certificate usually lists, for each item, the contract quantity, what was certified before, this period and the total to date. That layout, the automatic recovery and retention, and comparing your own progress with what the consultant certified are the main things contractors add to Odoo.
8. The project's margin
The project's margin report brings revenue and costs together by month. By the end of November it showed AED 674,400 of certified work, AED 73,728 of labour and AED 615,000 of subcontract costs, AED 688,728 in all.

It also showed the advance as AED 660,390 of revenue in September, which is the down payment setting from step 3. With that account set up, the report shows the certified work only.
The steps we did by hand, and what can go wrong
Standard Odoo got us through the whole project, but several steps were typed by hand on each invoice or bill, and Odoo didn't check them. To see how far that goes, we entered 5,000 m³ of backfilling as done against a BOQ quantity of 1,100 m³. Odoo accepted it and was ready to invoice 4,400 m³ that don't exist. It also accepted 150% of the MEP package as received from the subcontractor.
- Measured quantities on the contract. Typed on each line, with no limit at the BOQ quantity and no link to what the consultant certified. A typing error goes straight onto the client's invoice.
- Advance recovery. A line typed on each interim invoice, with its amount and its VAT. Nothing stops you recovering more than the advance, or forgetting the line, and the option that deducts the whole advance has to be turned off every time.
- Retention on both sides. A line typed on each client invoice and subcontractor bill. The rate, the account and the running total held per contract all depend on the person typing, and so does the release at the end.
- Subcontractor progress. The certified percentage is typed on the subcontract, with no cap at 100% and no approval before the bill.
- Variations. Added straight to the signed contract and billed with the next certificate, with no approval step and no register of what the client actually instructed.
- Settings that protect the figures: the down payment account and billing subcontracts on received quantities. Each is set once, and getting either wrong misstates revenue or pays a subcontractor too much.
On our construction projects we take these steps out of people's hands. The contract holds its own advance, recovery and retention rates, and each certificate works them out, stops recovery at the advance amount and keeps a retention balance per contract. Certified quantities can't pass the BOQ quantity without an approved variation, subcontractor certificates can't pass 100% or go out without approval, and variations move from request to instruction to approval before anything is invoiced. Odoo then prints the payment certificate with previous, current and cumulative amounts.
What else contractors in the UAE and Saudi Arabia need
Our test covered the commercial flow of one project. Contractors in both countries usually also need the following, which standard Odoo doesn't handle the way a contractor would expect:
- Guarantees and bonds: advance payment, performance and retention guarantees, with their amounts, the bank and the expiry date, and a reminder before each one lapses.
- Retention released in two steps: part at handover and the rest after the defects liability period, tracked per contract and per subcontract, as many contracts in the Gulf provide.
- Revenue over time: on long contracts, revenue is usually recognised by progress under IFRS 15, not by invoice, so work in progress and over- or under-billing need entries every month.
- A variation and claims register: variation requests, instructions, approvals and extension of time claims, with their status before anything reaches an invoice.
- Subcontractor control: back-charges, and checks on each subcontractor's trade licence, insurance and prequalification before an order is placed.
- Plant, stores and site: owned and hired equipment charged to projects, material requests from site with issues and wastage per project, and site documents such as drawings and revisions, transmittals, requests for information, submittals, non-conformance reports and incident reports.
- Workforce compliance: WPS salary files in the UAE, Mudad and GOSI in Saudi Arabia, visa and iqama expiries, and Emiratisation and Saudization quotas.
- Tax: VAT on advances and retentions, withholding tax in Saudi Arabia on payments to foreign suppliers and subcontractors, and corporate tax in both countries.
Some of this sits partly in Odoo apps such as Documents, Maintenance, Inventory and Payroll, and all of it can be built on Odoo for your contracts.
What Odoo 20 covers for a contractor
- Standard: tenders in CRM, the BOQ as a quotation with sections and units, BOQ import from a spreadsheet, the project and a task per BOQ item, the Gantt programme with dependencies, a cost budget per project, the advance invoice, subcontractor bids side by side, subcontractor progress bills, timesheets with labour cost, interim invoices on measured quantities, variations on the signed contract and the project's margin report. Our test used Odoo Enterprise: the Gantt view, the bids app and budgets are Enterprise features.
- A setup, no code: a down payment account for advances, billing subcontracts on received quantities, a retentions receivable and a retentions payable account, hourly costs for the site team, and your own tender stages.
- Added: checks that stop quantities and certificates passing the contract, cost sheets per BOQ item, a payment certificate layout with previous, current and cumulative amounts, automatic advance recovery and retention on both sides, progress compared with the consultant's certification, labour camps, salaries spread over projects, Primavera or Microsoft Project import, and site documents such as requests for information, submittals and non-conformance reports. These need Odoo.sh or your own server, since Odoo Online doesn't accept added modules.
The UAE and Saudi Arabia
The same flow runs in both countries, with each country's taxes and rules set up in Odoo's localization:
- VAT: 5% in the UAE and 15% in Saudi Arabia, with tax invoices in Arabic and English.
- E-invoicing: Saudi Arabia's ZATCA e-invoicing is already live, and Odoo's Saudi localization supports it. The UAE starts in 2027; our guide to UAE e-invoicing covers the deadlines and how Odoo connects.
- Payroll: UAE salaries go through the WPS, and gratuity follows the labour law; see our guide to UAE labour law and payroll.
Facade and glazing companies that manufacture before they install have their own article: Odoo for aluminium, glass and facade companies.
How NavyBits can help
NavyBits has been an official Odoo partner since 2017, with 10 Odoo-certified experts, and a senior engineer leads every project. We've implemented Odoo with local accounting, tax and payroll rules in Saudi Arabia, the UAE and four other countries, and connected Odoo to ZATCA e-invoicing. AKA Contracting in Saudi Arabia is among our Odoo references; see our page on Odoo for real estate and construction.
For a contractor we start with an assessment of how you tender, bill, buy, pay subcontractors and track costs today, and of the reports your client, consultant and auditor ask for. Then we set up the standard flow and build the rest around your contracts: payment certificates, automatic recovery and retention, approvals for variations and subcontractor certificates, and checks that stop wrong quantities and amounts before they reach an invoice. Every change is tested on a copy of your database first, and we keep the system current after go-live.
Book a free 30-minute call with a business consultant and an engineer. Bring one project's BOQ and a recent payment certificate, and we'll show you how they would run in Odoo.
FAQ
Can Odoo handle a bill of quantities (BOQ)?
Yes, as a quotation with sections, quantities, units and rates, imported from a spreadsheet. In our Odoo 20 test each BOQ item became a task in the project once the contract was confirmed. A cost sheet that breaks each item into materials, labour and equipment has to be added.
Does Odoo do progress billing for construction?
Yes. You enter the measured quantity on each contract line and Odoo invoices what was done since the last invoice, variations included. Advance recovery and retention were added as lines on each invoice in our test, and a certificate layout with previous and cumulative amounts needs a custom report.
Does Odoo stop you invoicing more than the BOQ quantity?
Not in standard Odoo 20. In our test it accepted 5,000 m³ certified against a BOQ quantity of 1,100 m³, and 150% of a subcontract package as received. Limits at the contract quantity, approvals and links to the consultant's certification have to be added.
How does Odoo handle retention?
There's no retention setting in standard Odoo 20. We used a retention line on each client invoice and subcontractor bill, posted to a retentions receivable or payable account. Automatic retention and its release at handover are common additions.
Can Odoo compare subcontractor bids?
Yes. In Odoo 20 the Purchase Alternative app links the bids for a package so you can compare them and award one. It compares price, dates and the vendor's on-time delivery, not quality or safety scores.
Does Odoo replace Primavera?
Odoo's Gantt view plans tasks with dependencies and is enough for many site programmes. Contractors who must submit programmes in Primavera or Microsoft Project usually keep them and connect them to Odoo, which needs an integration.
Is Odoo suitable for contractors in Saudi Arabia?
Yes. Odoo's Saudi localization covers 15% VAT, Arabic invoices and ZATCA e-invoicing, and the construction flow in this article works the same way there.